Work is progressing well on the second synthetic turf field at Kalka Shades, in preparation for the Oceania Cup in September.

All underground services are in place, field irrigation and pumps are ninety percent complete and the tech bench & toilet blocks are currently under construction.

The field shock pad is set to be installed next week, the light towers are up and the aluminum grandstands for shade seating areas are being fabricated. After speaking with the Project Manager in Rockhampton, the site is looking fantastic and everything is on track to allow Rockhampton to shine come September!